Images

Raunak City

Raunak Urban Centre

One of the largest townships in Kalyan is Raunak City, a sprawling community that spreads over thirty acres.

Stage-by-stage, the establishment is categorized into sectors, out of which, sectors 2 and 3 are currently active.

In Sector 4, you'll find ten high-quality towers that offer spacious and quality apartments.

The exquisite Raunak City, meticulously designed by world-renowned draughtsman Mr. Reza Kabul & Associates, is the pinnacle of opulence for anyone looking to live near a city like Mumbai.

This township offers a vast range of homes, from spacious 1 BHK apartments to a pristine clubhouse equipped with a play area for kids and a well-equipped gym, which enhances the experience.

An opulent swimming pool serves as a welcome escape from the mundane, transforming it into a delightful experience unmatched by any other.

Overview
Project Location Raunak City Road, Kalyan (W)
Construction Status

  • D8 - 20th habitable slab completed

Starting Price 1 BHK - ₹ 42 Lacs only
Configuration 1BHK, 2BHK
Construction Funding Partner icici-hfc-logo
BROCHURE Brochure
Home Loans hdfc-logo  icici-bank  lic-logo  sbi-logo
QR Codes
Images
Images
Images
Images
Images
Images
Images
Images
Location
Images
Highlights
Icon

Your Most-loved Food Joints

Icon

Unparalleled Shopping Experiences

Icon

Branded Salon & Spa

Icon

Zero wastage, smartly designed homes

Icon

Separate toilet bath area, fitting with Jaquar

Icon

A spacious bedroom with ample room for wardrobe

Icon

Vast kitchen space created by Sleek

Icon

Wide living area with dining area plus a niche

Icon

Designer vitrified tiles in all rooms

Icon

Dry balcony for washing machine and kitchen

Icon

Sundeck in every room

Images
Amenities
Icon

Air-conditioned Gym

Icon

Kids Play Area

Icon

Landscaped Garden

Icon

Infinity edge swimming pool

Icon

Kids swimming pool

Icon

Wifi-enabled work pods

Icon

Indoor Games room

Icon

Skating rink

Icon

Party lawn

Icon

Banquet Hall

Icon

Small library nook

Icon

Jogging Track

Icon

Senior citizens corner

Plans
Sector 4 Master Plan
Floor Plan - D9/D4 - 1 BHK
Floor Plan - D7/D8 - 2 BHK
360 Degree
Virtual Runway
1 BHK
2 BHK
Site Progress
  • Raunak City Site Progress

    February, 2022(D8 - 20th habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D7 - 20th habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D5 - 8th habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D4 - 21st habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D8 - 19th habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D7 - 19th habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D6 - 7th habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D5 - 7th habitable slab completed)

  • Raunak City Site Progress

    January, 2022(D8 - 18th habitable slab completed)

  • Raunak City Site Progress

    December, 2021(D5 - 6th habitable slab completed)

  • Raunak City Site Progress

    December, 2021(D8 - 17th habitable slab completed)

  • Raunak City Site Progress

    November, 2021(D6 - 5th habitable slab completed)

  • Raunak City Site Progress

    November, 2021(D8 - 16th habitable slab completed)

  • Raunak City Site Progress

    November, 2021(D7 - 16th habitable slab completed)

  • Raunak City Site Progress

    October, 2021(D8 - 15th habitable slab completed)

  • Raunak City Site Progress

    October, 2021(D7 - 15th habitable slab completed)

  • Raunak City Site Progress

    October, 2021(D6 - 4th habitable slab completed)

  • Raunak City Site Progress

    October, 2021(D5 - 4th habitable slab completed)

  • Raunak City Site Progress

    October, 2021(D8 - 14th habitable slab completed)

  • Raunak City Site Progress

    October, 2021(D7 - 14th habitable slab completed)

  • Raunak City Site Progress

    October, 2021(D6 - 3rd habitable slab completed)

  • Raunak City Site Progress

    May, 2021(D8 - 16th habitable slab completed)

  • Raunak City Site Progress

    December, 2020(D3 - 15th habitable slab completed)

  • Raunak City Site Progress

    November, 2020(D4 - 20th habitable slab completed)

  • Raunak City Site Progress

    March, 2020(D7 & D8 - Plinth completed)

  • Raunak City Site Progress

    March, 2020(D4 - 15th habitable slab completed)

  • Raunak City Site Progress

    February, 2020(D5 - Excavation work started)

  • Raunak City Site Progress

    February, 2020(D4 - 14th habitable slab completed)

  • Raunak City Site Progress

    January, 2020(D4 - 13th habitable slab completed)

  • Raunak City Site Progress

    January, 2020(D4 - 12th habitable slab completed)

  • Raunak City Site Progress

    December, 2019(D3 - 8th habitable slab completed)

  • Raunak City Site Progress

    December, 2019(D9 - 23rd alan completed)

  • Raunak City Site Progress

    December, 2019(D4 - 11th habitable slab completed)

  • Raunak City Site Progress

    December, 2019(D3 - 7th habitable slab completed)

  • Raunak City Site Progress

    December, 2019(D9 - 22th habitable slab completed)

  • Raunak City Site Progress

    December, 2019(D4 - 10th habitable slab completed)

  • Raunak City Site Progress

    November, 2019(D4 - 9th habitable slab completed)

  • Raunak City Site Progress

    November, 2019(D3 - 6th habitable slab completed)

  • Raunak City Site Progress

    November, 2019(D9 - 21st habitable slab completed)

  • Raunak City Site Progress

    November, 2019(D4 - 8th habitable slab completed)

  • Raunak City Site Progress

    November, 2019(D9 - 20th habitable slab completed)

  • Raunak City Site Progress

    November, 2019(D4 - 7th habitable slab completed)

  • Raunak City Site Progress

    October, 2019(D3 - 4th habitable slab completed)

  • Raunak City Site Progress

    October, 2019(D4 - 6th habitable slab completed)

  • Raunak City Site Progress

    October, 2019(D9 - 19th habitable slab completed)

  • Raunak City Site Progress

    October, 2019(D7 & D8 - foundation work started)

  • Raunak City Site Progress

    October, 2019(D3 - 3rd habitable slab completed)

  • Raunak City Site Progress

    October, 2019(D4 - 5th habitable slab completed)

  • Raunak City Site Progress

    October, 2019(D9 - 18th habitable slab completed)

  • Raunak City Site Progress

    September, 2019(D4 - 3rd habitable slab completed)

  • Raunak City Site Progress

    September, 2019(D9 - 17th habitable slab completed)

  • Raunak City Site Progress

    September, 2019(D3 - 1st habitable slab completed)

  • Raunak City Site Progress

    August, 2019(D9 - 15th habitable slab completed)

  • Raunak City Site Progress

    August, 2019(D4 - 1st habitable slab casted)

  • Raunak City Site Progress

    July, 2019(D9 - 13th habitable slab completed)

  • Raunak City Site Progress

    June, 2019(D9 - 12th habitable slab completed)

  • Raunak City Site Progress

    May, 2019(D9 - 11th habitable slab completed)

  • Raunak City Site Progress

    April, 2019(D9 - 10th habitable slab completed)

  • Raunak City Site Progress

    March, 2019(D9 - 7th habitable slab completed)

  • Raunak City Site Progress

    February, 2019(D9 - 7th habitable slab completed)

  • Raunak City Site Progress

    February, 2019(D9 - 6th habitable slab completed)

  • Raunak City Site Progress

    February, 2019(D10 - External painting work started.
    D9 - 5th habitable slab completed)

  • Raunak City Site Progress

    December, 2018(D1/D2 - Painting work ongoing
    D10 - Internal work ongoing
    D9 - 2nd habitable slab completed
    D3 - Foundation work ongoing
    D4 - Excavation work completed
    Club house work ongoing
    Landscape garden plantation
    work ongoing.)

  • Raunak City Site Progress

    December, 2018(D9 - 2nd habitable slab completed)

  • Raunak City Site Progress

    December, 2018(D1/D2 - Painting work ongoing
    D10 - Internal work ongoing
    D9 - 2nd habitable slab cmpleted
    D3 - Foundation work ongoing
    D4 - Excavation work completed
    Club house work ongoing
    Landscape garden plantation
    work ongoing.)

  • Raunak City Site Progress

    November, 2018(D9 - 1st habitable slab completed)

  • Raunak City Site Progress

    October, 2018(D1 & D2
    External painting started
    D10 - Internal plaster started
    D9 - 1st habitable slab preparation)

  • Raunak City Site Progress

    October, 2018(D9 - Plinth completed)

  • Raunak City Site Progress

    October, 2018(D1, D2 & D10
    External painting started)

  • Raunak City Site Progress

    July, 2018

  • Raunak City Site Progress

    June, 2018

  • Raunak City Site Progress

    March, 2018

  • Raunak City Site Progress

    February, 2018

  • Raunak City Site Progress

    January, 2018

  • Raunak City Site Progress

    December, 2017

  • Raunak City Site Progress

    October, 2017

  • Raunak City Site Progress

    July, 2017

  • Raunak City Site Progress

    June, 2017

  • Raunak City Site Progress

    May, 2017

  • Raunak City Site Progress

    February, 2017

  • Raunak City Site Progress

    November, 2016

Why Kalyan?

Kalyan is quickly transforming into a major metropolis in MMR

  • Upcoming 24 Km Metro line enroute Taloja-Shilphata-Kalyan
  • Proposed six-lane bridge on Ulhas river
  • Proposed freeway from Airoli (near Thane) to Katai Naka (near Kalyan)
  • KDMC to develop Kalyan Creek on lines of Sabarmati Riverfront
  • Proposed growth city on the lines of Bandra Kurla Complex